General

Procedure and timing for an environmental permit

Procedure and timing for an environmental permit

In most cases, you need an environmental permit before you can start your project. This article gives you an overview of the different steps involved in obtaining one.

This subject may seem dull and tedious, but this overview will help you form a realistic idea of what to expect when you need an environmental permit. We hope you find it useful.

When a permit is required

The environmental permit covers what were previously separate permits for building, environmental matters and land subdivision. Whether you want to put up a carport or construct an entirely new building, the environmental permit rules apply in both cases. The scale of the project makes no difference. The regulations state: 

“No one may, without first obtaining an environmental permit for urban development works:

• erect or place a structure;
• combine materials for a functional purpose to create a structure;
• demolish, rebuild, alter or extend a structure;
• …” 

There are, of course, exceptions. Very small-scale projects, such as constructing a driveway, may be exempt. Always check whether an exemption applies. If none does, you need an environmental permit.  

The different steps

The environmental permit application process involves several steps. The first and most important is preparing the application. At this stage, you find out what requires a permit, draw up plans with or without an architect, and provide reasons for your application. 

You then submit your application, starting an initial 30-day period in which it must be declared complete and admissible. During this period, the authorities check whether your application is complete. Have you forgotten something, or do they need further information? The procedure will be suspended or you will be asked to provide additional information. Once the new information has been submitted, the authorities have another 30 days to check it.  

As soon as your application is declared complete, its substance is assessed. This takes a maximum of 60 days for straightforward applications and a maximum of 105 or 120 days for other applications. You must receive a decision on your application within this period. These maximum time limits are often used up because of the large volume of permit applications.  

A public inquiry may be held while your application is being assessed. During the 30-day inquiry period, you must display a yellow public notice. Local residents can view the application and submit any objections during this time. An objection does not automatically mean your application will be refused, but it does require additional attention!  

External bodies are also asked to provide advice during this period. The most common advisory bodies are the Department of Agriculture and Fisheries, the Watercourses Department, an intermunicipal heritage organisation, and the Agency for Nature and Forests. Companies such as Telenet and Fluvius may also be asked for advice.  

If issues arise during the substantive assessment, such as an error, an objection or an unfavourable opinion, the plans submitted with the application may still be amended. This is done by means of a request to amend the application. This allows you to change or correct certain elements. The decision period may be extended by 60 days when such a request is made. If a procedural error has occurred, the application may also be extended by 60 days through an administrative loop.  

Finally, a decision must be made on your application within the time limit. It is assessed by the municipal executive, or by the provincial executive. They decide on your application based on your documents, any objections and the advice received. They also receive a final recommendation from the chief official of the Environment Department, proposing whether or not to grant the permit. 

The decision

Once a decision has been made on your application, you must display it for 30 days in a clearly visible place along a public road. This requirement applies if the permit is granted, and usually also if it is refused. During this period, interested parties have the opportunity to appeal. They have 35 days to do so, which is 5 days longer than the notice must be displayed. If no appeal is lodged, you may start carrying out the work covered by your permit.  

Accordingly, a straightforward application takes around 30+60+35 days, excluding preparation time, or approximately four months. 

For other projects, the application takes around 30 +105+ 35 days, excluding preparation time, or approximately five months.  

In both cases, the process may be extended by a further 60 days through a request to amend the application or an administrative loop. 

Would you like support with your environmental permit application? Contact a DLV adviser at [email protected] or on the freephone number 0800 90 910.   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow on GreenPro Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.